It takes time and meticulous work.
Two weeks ago we set the initial process of installing the bond beams and today the work continuous. Digging two feet deep is necessary to receive the steel foundation required in the stabilization for the three floors.
More work is being done on the stone exterior grouting.
The next 2 shots show the bond beams which will be supported by the steel frame which we hope will be in place in 30 days.
A closer shot of the digging done for the foundation for the first floor and 2 feet beyond that, as required for the elevator to service the 3 floors of the building.